Assembly-line fixture refresh
BriefLine changeover needed 18 new locating fixtures; the in-house machine shop was booked for 7 weeks.
What we printedPETG fixture bodies with PA-CF locating inserts, printed overnight in three batches.
- Material
- PETG + PA-CF
- Tolerance
- ±0.2 mm
- Lead time
- 54 h for all 18 fixtures
Changeover hit its original date; fixture cost 74 % below the machined equivalent.